Summer 2026 Road Work projects

American Asphalt will be paving and shouldering  DAMRAU ROAD (.5 mile or ~2,645’ from County Q to Town of Amherst line) at a cost of $56,973.20

American Asphalt will also pave and shoulder FLOISTAD ROAD (~2,007 x 18’ from County Road T to Town of Amherst portion) at a cost of $47,748.80

In addition, the culvert on Durant Road (a site prone to flooding) was replaced with two 24" metal culverts and the surface of the road was lifted with limestone.  This work cost just under $25,000.  The plan is to allow traffic to further compress the newly applied stone with paving to occur in 2027, although the Town is exploring the possibility of paving later in 2026 if the budget allows it.

Finally, Crack Filling Service (Cross plains, WI) will be filling cracks on Oakdale (west of TT), Madley, Riley, Old Amish, Clinton and Morgan roads at a cost not to exceed $25,000